The financing of the first stage of NDF is provided

21.06.2013

A grant agreement for the KIDSF money for construction of the first stage of the National Disposal Facility for low and intermediate radioactive waste (NDF) was signed on 20 June 2013 between Dilyan Petrov, Executive Director of SERAW and Vince Novak, Director of Nuclear Safety Department at the European Bank for Reconstruction and Development (EBRD). The ceremony, at which an agreement for rehabilitation of the heating system of Sofia from the KIDSF “non-nuclear window” was signed, was attended by Dragomir Stoynev, Minister of Economy and Energy. He said that the money have serious contribution for the Bulgarian energy sector and the economy. He also said that the realization of the two projects would add one more step in our mutually beneficial relationship with the KIDSF. Minister Stoynev emphasized that the grant agreement will contribute for Bulgaria to fulfill the IAEA criteria for sustainable radioactive waste management.

“These are two very important projects, a result from the continuous efforts of the Bulgarian state for the last few years”, Vince Novak said. He said he would not like to compare the priority of the projects but defined the “non-nuclear” project as important for the capital city and the future disposal facility – as especially important for the country as a whole.

Dilyan Petrov expressed his deep gratitude to the teams who contributed for the signing of the agreement. He summarized that thanks to the last factor – provision of financing, the implementation of the follow-up activities could be started as almost the whole preliminary work was already completed – all legal procedures were implemented and the Technical Design of the facility was accepted. As result of all this the requirements of the National Strategy for Management of Spent Nuclear Fuel and Radioactive Waste will be met – at the end of 2015 the disposal facility will be in operation. NDF is of significant importance for the successful realization of the safe decommissioning activities of Units 1-4 of Kozloduy NPP.


The construction of NDF is a national priority for Bulgaria.

The project was assigned to SERAW with Council of Ministers Decision № 683/25.07.2005. With decision of the government the disposal facility received a status of national importance, and with additional decision it was pronounced to be a strategic site in regard to the national security. Six years later, on 7 December 2011 the commitment of the state was confirmed at highest level with amendment to the decision of the Council of Ministers with which the project for construction of disposal facility at Radiana site received a status of national importance.

SERAW started the project activities after receiving permission from NRA for selection of site in May 2006. In the follow-up period the SERAW experts conducted huge number of surveys, studies, analyses and assessments, meeting the requirements of the Bulgarian legislation, the EU and in compliance with the IAEA standards, and applying the best international practices.

Considering the progress of the country in implementation of the NDF programme, the 25-th Assembly of Donors of KIDSF, which took place on 14 June 2013, approved the signing of a Grant Agreement for construction of the first stage of the facility where the RAW from the decommissioning

of Units 1-4 will be disposed. The money from the Grant Agreement will finance the following activities:

of Units 1-4 will be disposed. The money from the Grant Agreement will finance the following activities:

Construction of the first module for RAW disposal with capacity 6 336 concrete containers and adjacent buildings and facilities, supply of systems and equipment, installation and testing, receiving an operation license;

Independent construction supervision and supervision of the construction of the first stage;

Preparation of the licensing documentation for decommissioning and receiving a license in compliance with the nuclear regulation.